Category: Work in progress
-
Mid Week Check-in 6/23/2022
Charles started a white soffit and black fascia in Towanda Il Dave removed cedar shake siding, installed proper flashing, installed new cedar shake and painted to match Josh replaced incorrect flashing on a chimney in bloomington il Ricky installed new storm windows in Bloomington IL and fixed a bad leak where the gutter meets the…
-
Mid Week Check-in 6/16/2022
Bryant and his crew are almost finished with their vinyl siding replacement. This home is getting Mastic Natural slate Board and Batten siding and Mastic Red Cedar Shakes Charles installed Mastic Cape Cod Shakes where brick was removed on this property Brad and his crew have been installing new construction gutters and fixing residential seamless…
-
Mid Week Check-in 6/9/2022
Joe’s crew has been continuing to make great headway on a vinyl siding replacement project. They have needed to replace the framing around one of the doors. Joe also slipped in a few minor siding repairs while the rain was being spotty. Josh has been doing a lot of big roof repairs. Almost all of…
-
Mid Week Check-in 6/2/2022
Johnney added a storm door to an entry door and then he installed tyvek on a home that was partially tyveked. He is also repairing steel siding while he is there. Josh repaired a roof that had a few humps in the roof. He removed the shingles, cut out the warped plywood, installed underlayment, and…
-
Mid Week Check-in 5/26/2022
Nathan is almost finished replacing the cedar siding on this local hotel with LP Smartside siding. He also fixed some loose soffit at an Apartment complex before it fell down. Johnney has been working on house that was originally installed incorrectly where the roof line meets the siding. Then a second layer of shingles was…
-
Mid Week Check-in 5/18/2022
Bryant’s crew is getting close to wrapping up this new construction siding job. We should have finished photos this time next week. Nathan’s crew has been removing cedar siding off this local hotel and installing LP Smartside in a custom color. They should be finished in around 1 week. Joe’s crew has started a new…
-
Mid Week Check-in 5/11/2022
In-between new construction gutter installs, Brad’s crew replaced rotted fascia boards, installed new fascia metal, and ran new seamless gutters and downspouts. Johnney has been doing multiple wind damaged soffit, fascia, and siding repairs. We recently had some high winds from a tornado watch and many homes have small repairs from the wind damage. Bryant’s…
-
A Look Into Our Work Week
Mitchell has replaced a few dented garage door panels and installed 3 garage doors this week. Jayden has been helping Dave out with some larger projects but in-between he has performed some roof repairs – blown off shingle install, damaged shingle and drip edge replacement. Dave has been working on some larger projects this week.…
-
A Look Into Our Work Week
Joe and his crew completed installing new siding on a home. They used Sandstone (tan siding) with Royal brown soffit and fascia. Since they completed that they started updating the look of a home by replacing the trim boards with new. Joe has been working very closely with the homeowner to achieve the look she…
-
A Look Into Our Work Week
Mitchell usually works alone installing garage doors but this week he teamed up with Brad to install 2x the amount each day. In 3 days they installed 7 garage doors with chain drive openers on each one- WOW! Nathan and his crew have almost finished replacing the siding on this home. The natural slate dark…